The James Webb Space Telescope (JWST) is the largest space telescope, designed for infrared astronomy. Its advanced instruments offer unprecedented resolution and sensitivity, surpassing the Hubble Space Telescope. This enables JWST to observe incredibly distant and faint objects, including the first stars and galaxies. Its capabilities extend to characterizing the atmospheres of potentially habitable exoplanets, significantly advancing our understanding of the universe's origins and the potential for life beyond Earth.
James E. Webb assumed the role of NASA administrator in 1961.
James E. Webb concluded his tenure as NASA administrator in 1968.
The Hubble Space Telescope project formally commenced in 1972 with an estimated development cost of US$300 million.
In 1984, the Space Science Board conducted a study estimating the cost of constructing a next-generation infrared observatory in orbit. Their projection placed the expense at US$4 billion.
The development of the Hi-Z telescope concept, an early predecessor to the James Webb Telescope, took place between 1989 and 1994.
The Hubble Space Telescope was launched into orbit in 1990.
NASA conducted the STS-61 Space Shuttle mission in 1993 to correct the flawed optics of the Hubble Space Telescope. This mission involved replacing the telescope's camera and installing a retrofit for its imaging spectrograph to address the spherical aberration in its primary mirror.
The HST & Beyond Committee was established in 1994 to explore potential missions and programs for optical-ultraviolet astronomy in space for the early 21st century.
The Hi-Z telescope concept, a 4-meter aperture infrared telescope intended for a distant orbit, was finalized in 1994.
In 1996, the HST & Beyond Committee released a report exploring the concept of a larger, colder, infrared-sensitive telescope that could peer back in time to the formation of the first galaxies. This report emphasized the scientific need for a telescope capable of observing in infrared wavelengths, which the existing Hubble Space Telescope couldn't do effectively due to its own infrared emissions.
The collaboration between NASA, ESA, and CSA on the James Webb Space Telescope project originated in 1996. This partnership brought together the expertise and resources of these space agencies to tackle the ambitious endeavor.
The initial design concepts for the telescope, then known as the Next Generation Space Telescope, were initiated in 1996.
In 1997, NASA collaborated with Goddard Space Flight Center, Ball Aerospace & Technologies, and TRW to conduct technical requirement and cost studies for three different concepts of the Next Generation Space Telescope (NGST).
Two concept studies for the Next Generation Space Telescope were commissioned in 1999, targeting a potential launch in 2007 with a budget of US$1 billion.
NASA selected Lockheed Martin and TRW in 1999 for preliminary concept studies of the NGST.
The Next Generation Space Telescope (NGST) received the highest ranking in the 2000 Decadal Survey, highlighting its importance as a scientific priority.
In preparation for the 2000 Astronomy and Astrophysics Decadal Survey, NASA further developed the scientific program for the Next Generation Space Telescope, refining its goals of studying galaxy formation and searching for exoplanets.
In 2002, NASA administrator Sean O'Keefe named the telescope after James E. Webb, who served as the administrator of NASA from 1961 to 1968.
The Next Generation Space Telescope was renamed in 2002 to the James Webb Space Telescope, in honor of James E. Webb, NASA's second administrator.
In 2003, ESA's member states formally endorsed the agency's participation in the construction and launch of the James Webb Space Telescope, solidifying their commitment to the project.
In 2003, the Space Telescope Science Institute (STScI) was chosen to operate the James Webb Telescope, responsible for its scientific operation and data distribution.
NASA awarded TRW the prime contract for the James Webb Space Telescope in 2003.
The European Space Agency (ESA) pledged approximately €300 million towards the James Webb Space Telescope project in 2004, including providing the launch vehicle.
The James Webb Space Telescope project underwent a significant re-planning phase in August 2005 due to cost overruns. Key changes included adjustments to integration and testing procedures, a 22-month launch delay (from 2011 to 2013), and the elimination of full-system testing at certain wavelengths.
In 2005, the life-cycle cost for the James Webb Space Telescope was estimated to be around US$4.5 billion.
The HST & Beyond Committee recommended extending the Hubble Space Telescope mission to 2005.
The James Webb Telescope underwent a major redesign in 2005.
Following the re-planning efforts, the James Webb Space Telescope project underwent an independent review in April 2006.
By 2006, the overall cost of the Hubble Space Telescope, including instruments and servicing missions, had reached at least US$9 billion.
The 1984 cost estimate of US$4 billion, when adjusted for inflation to reflect 2006 dollars, amounted to US$7 billion.
In January 2007, nine out of ten technology development items for the James Webb Space Telescope successfully passed a Non-Advocate Review, signifying their maturity and reduction of project risks.
The final technology development item, the MIRI cryocooler, reached its technology maturation milestone in April 2007, paving the way for the project's detailed design phase.
As of May 2007, the James Webb Space Telescope project remained within budget.
The Canadian Space Agency (CSA) committed CA$39 million to the James Webb Space Telescope project in 2007.
The initial timeline for the James Webb Space Telescope project aimed to achieve mechanical integration by 2007. However, this milestone faced delays and was eventually accomplished in 2019.
A significant milestone was reached in 2007 when ESA and NASA formalized their collaboration on the James Webb Space Telescope project through a signed agreement.
The James Webb Space Telescope project successfully completed its Preliminary Design Review (PDR) in March 2008.
The James Webb Space Telescope project passed the Non-Advocate Review in April 2008, indicating progress and adherence to requirements.
By 2008, the James Webb Space Telescope project had progressed to the preliminary design review stage and received formal confirmation for construction. By this point, over US$1 billion had been invested in developing the telescope, and the total budget was projected to be around US$5 billion.
The Integrated Science Instrument Module for the James Webb Space Telescope successfully passed review in March 2009.
The Optical Telescope Element of the James Webb Space Telescope successfully completed its review in October 2009.
The sunshield designed for the James Webb Space Telescope underwent and passed a successful review in January 2010.
The James Webb Space Telescope passed the technical evaluation of its Mission Critical Design Review (MCDR) in April 2010, indicating its ability to meet mission requirements.
Around 2010, as the James Webb Space Telescope project faced mounting expenses and schedule setbacks, concerns began to surface within the scientific community. Scientists expressed worry that the escalating budget of the telescope might be diverting resources from other valuable space science programs. This concern was highlighted in a 2010 article in the journal Nature, which dubbed the James Webb Space Telescope "the telescope that ate astronomy." Despite these anxieties, NASA remained steadfast in its defense of the program's budget and timeline to Congress.
During the summer of 2010, the James Webb Space Telescope mission successfully passed its Critical Design Review (CDR), receiving excellent assessments on all technical fronts. However, concerns arose due to schedule slips and cost overruns. These issues prompted Maryland U.S. Senator Barbara Mikulski to request an external review of the project.
At this time, the planned launch date for the James Webb Space Telescope was set for 2010.
In July 2011, the United States House of Representatives' appropriations committee on Commerce, Justice, and Science made a move to cancel the James Webb Space Telescope project. Their proposal involved an FY2012 budget that cut US$1.9 billion from NASA's overall budget, with approximately a quarter of this reduction intended for the James Webb project. At this point, US$3 billion had been spent, and 75% of the telescope's hardware was already in production.
In a reversal of the earlier decision to cancel the James Webb Space Telescope project, Congress, in November 2011, decided to continue the project. Instead of cancellation, they implemented a cap on additional funding, limiting it to US$8 billion to complete the project.
By 2011, the James Webb Space Telescope project had progressed to its final design and fabrication phase (Phase C).
The initial target for launching the James Webb Telescope was set for 2011.
The Canadian Space Agency delivered its contributions to the James Webb Space Telescope project in 2012, providing equipment for precise pointing and atmospheric characterization of distant planets.
The target launch date for the James Webb Telescope was revised to 2013.
Assembly of the hexagonal segments comprising the primary mirror of the James Webb Space Telescope commenced in November 2015, utilizing a robotic arm for this intricate process.
The star KIC 8462852, notable for its unusual light patterns, was discovered in 2015. It's been suggested that the James Webb telescope could be used to learn more about this star.
The assembly of the James Webb Telescope spacecraft bus, responsible for supporting and maneuvering the telescope, was finalized in California in 2015.
The Independent Comprehensive Review Panel (ICRP), led by J. Casani of JPL, concluded that the earliest possible launch date for the James Webb Space Telescope was in late 2015. This projection came with an estimated additional cost of US$1.5 billion, bringing the total to US$6.5 billion.
Following the Mission Critical Design Review, an Independent Comprehensive Review Panel reevaluated the project schedule and set a target launch date for the James Webb Space Telescope in 2015.
In 2015, concerns were raised about James Webb's potential involvement in the lavender scare, a period in the mid-20th century where the U.S. government persecuted homosexuals in federal employment.
On February 3, 2016, the assembly of the James Webb Space Telescope's primary mirror, consisting of hexagonal segments, was successfully finished.
On March 3, 2016, the secondary mirror of the James Webb Space Telescope was installed.
Construction of the James Webb Space Telescope reached completion in November 2016, marking a significant milestone and the start of rigorous testing procedures.
The construction of the James Webb Telescope was completed in 2016.
In November 2017, the Space Telescope Science Institute announced 13 Director's Discretionary Early Release Science programs, aiming to gather observations during the first five months of Webb's operation.
Citing the need for more time, NASA announced on March 27, 2018, a postponement of the James Webb Space Telescope launch to May 2020 or later. This decision was made in consultation with the European Space Agency (ESA), and a definitive cost estimate was to be determined once a new launch window was established.
NASA announced a postponement of the James Webb Space Telescope's launch in March 2018, pushing it back by an additional two years to May 2020. This delay stemmed from a mishap during a practice deployment where the telescope's sunshield tore, coupled with insufficient tension in the sunshield's cables.
In June 2018, NASA made the decision to further delay the launch of the James Webb Space Telescope by an additional 10 months, moving the target to March 2021. This decision followed an assessment by an independent review board convened after a test deployment failure in March 2018.
The Independent Comprehensive Review Panel, tasked with assessing the James Webb Space Telescope project, acknowledged the possibility of the launch being delayed until 2018.
In 2018, during the deployment testing phase, the James Webb Telescope encountered delays due to accidental tears in the delicate film structure of the sunshield.
Gregory L. Robinson took on the role of director for the James Webb Space Telescope program in 2018. His leadership proved instrumental in significantly enhancing the program's schedule efficiency, which measures the timely completion of tasks. Under his guidance, the schedule efficiency surged from 50% to an impressive 95%.
August 2019 marked a significant achievement in the James Webb Space Telescope project as the mechanical integration of the telescope was finalized. Notably, this accomplishment occurred 12 years later than originally planned in the project timeline.
In 2019, the mission cost cap for the James Webb Space Telescope project was raised by US$800 million. This adjustment reflected the ongoing work and resources required to ensure the mission's success.
After a reassessment in March 2018, the launch of the James Webb Space Telescope was rescheduled to take place no earlier than May 2020. This timeframe provided additional leeway for final preparations and coordination.
After encountering a setback with the sunshield in March 2018, NASA set a revised target launch date for the James Webb Space Telescope to May 2020 or later.
When factoring in inflation to 2020 dollars, the 1984 cost estimate of US$4 billion reached US$10 billion.
Following a delay announced in June 2018, the target launch date for the James Webb Space Telescope was shifted to March 2021.
On March 2021, the selection of Cycle 1 GO programs for the James Webb Space Telescope was announced, with 266 programs approved out of 1,173 submitted proposals.
On September 26, 2021, a ship transporting the James Webb Space Telescope embarked on its journey from California.
After its journey from California, the ship carrying the James Webb Space Telescope successfully traversed the Panama Canal and reached French Guiana on October 12, 2021.
The James Webb Telescope was launched on December 25, 2021, at 12:20 UTC aboard an Ariane 5 rocket from the Guiana Space Centre. The telescope's power supply was confirmed, marking the start of its deployment phase.
The James Webb Telescope was launched in December 2021 from French Guiana aboard an Ariane 5 rocket.
On December 30, 2021, mission controllers successfully deployed the aft "momentum flap" on the James Webb Telescope. This device helps maintain the telescope's orientation by counteracting solar pressure on the sunshield, which conserves fuel.
About 12 hours after its launch on December 25, 2021, the James Webb Telescope successfully completed its first mid-course correction using its primary rockets. On the second day, the high-gain communication antenna was automatically deployed.
On December 27, 2021, the James Webb Telescope successfully completed its second mid-course correction maneuver. The multi-day process of deploying the telescope's critical sunshield began on December 28, 2021.
The spacecraft bus was integrated with the James Webb Telescope leading up to its launch in 2021.
After experiencing delays due to the COVID-19 pandemic, which caused pauses in launch windows during 2020, the James Webb Space Telescope was successfully launched at the end of 2021. The total cost of the project reached just under US$10 billion.
Between December 31, 2021, and January 4, 2022, the ground team successfully extended the two telescoping "mid booms" on the James Webb Telescope. On January 5, 2022, mission control confirmed the successful deployment and locking of the telescope's secondary mirror with a precision of about one and a half millimeters.
In January 2022, the James Webb Telescope arrived at its designated orbit around the Sun-Earth L2 Lagrange point, situated about 1.5 million kilometers from Earth.
On January 12, 2022, while the James Webb Telescope was still in transit to its final destination, the process of aligning its mirrors began. The primary mirror segments and the secondary mirror were moved from their secure launch positions to prepare for focusing.
On January 24, 2022, at 2:00 p.m. Eastern Standard Time, the James Webb Telescope underwent its third and final course correction. This maneuver successfully placed the telescope into its intended halo orbit around the Sun-Earth L2 point, marking the end of its major travel adjustments.
On January 24, 2022, the James Webb Telescope successfully reached its designated halo orbit around the Sun-Earth L2 point, following a month-long journey that included three planned course corrections.
On January 7 and 8, 2022, the James Webb Telescope team successfully deployed and locked the port-side and starboard-side mirror wings. These wings, containing the primary mirror segments, were folded for launch and had to be unfolded in space. This marked the completion of the observatory's structural deployment.
On February 3, 2022, NASA announced that the James Webb Telescope's Near Infrared Camera (NIRCam) had detected its first photons. By February 11, 2022, the telescope had nearly finished phase 1 of its alignment process, with each segment of its primary mirror capturing images of the target star HD 84406. Phase 1 alignment was successfully completed on February 18, 2022, followed by the completion of phases 2 and 3 a week later. This achievement signified that all 18 mirror segments were functioning together.
Between May 23 and 25, 2022, the James Webb Telescope's C3 mirror segment was hit by a micrometeoroid, the fifth and largest impact since launch. This event was reported on June 8, 2022.
Despite the micrometeoroid strike, a NASA report on July 10, 2022, stated that all of the James Webb Telescope's observation modes were ready for scientific use.
The James Webb Space Telescope completed its commissioning phase in July 2022 and was declared ready to commence full scientific operations.
The first image captured by the James Webb Telescope was unveiled to the public in July 2022.
July 2022 marked the official start of Webb's general science operations with the release of its first full-color images and spectroscopic data.
On July 14, 2022, NASA presented images of Jupiter and its surrounding regions captured by the James Webb Space Telescope, including views in infrared.
After a distinguished 33-year tenure at NASA, Gregory L. Robinson, the director of the James Webb Space Telescope program, announced his retirement in July 2022. This decision followed the successful commissioning of the telescope, marking the beginning of its operational phase and the transmission of its inaugural data.
In August 2022, following the release of the first Webb images, several preprint papers reported the discovery of high redshift and very luminous galaxies, potentially dating back to 235-280 million years after the Big Bang.
In September 2022, primordial black holes were suggested as a possible explanation for the unexpectedly large and early galaxies observed by the James Webb Space Telescope.
In 2022, NASA released a report based on over 50,000 documents stating they found no evidence directly linking James Webb to any actions related to the firing of individuals based on their sexual orientation during his time at the State Department or NASA.
On May 10, 2023, the Cycle 2 GO program for the James Webb Space Telescope was announced, marking another round of observation proposals and allocations.
In June 2023, the James Webb Space Telescope detected organic molecules located 12 billion light-years away in a galaxy named SPT0418-47.
NASA celebrated the first year of operations for the James Webb Space Telescope in July 2023 by releasing an image of the Rho Ophiuchi cloud complex, a star-forming region located 390 light-years away.
In September 2023, based on recent studies conducted using the James Webb Space Telescope, two astrophysicists raised questions about the established Standard Model of Cosmology.
In December 2023, NASA released a series of images captured by the James Webb Space Telescope with a holiday theme, including views of the Christmas Tree Galaxy Cluster.
The estimated total budget of US$5 billion for the James Webb Space Telescope project in 2008, when adjusted for inflation to reflect 2023 dollars, amounted to US$7.8 billion.
In May 2024, the James Webb Space Telescope identified the most distant galaxy known to date, JADES-GS-z14-0, dating back to just 290 million years after the Big Bang.
The James Webb Space Telescope detected the most distant known black hole merger in May 2024, occurring within the galaxy system ZS7 just 740 million years after the Big Bang.